Saturday, November 27, 2010

Window frames in, gutters next!


Went to the block today to find the all the window frames in. It is very wet & more rain to come in the next few days. Gutters & the fascias were also ready to put up. Took plenty of photos.
Above/Below: Home theater room with raised floor with steps


Above: Dining room looking into Lounge/family room

Above: Laundry

Above: End of Dining room

Above: Lounge/Family room windows

Above: Study Window

Above: 5th Bedroom window

Above: Main Bedroom window

Above: En-suite shower window (will add frosting film when we move in)


Above: WIR window

Above: Study opening into Lounge/Family room (will add wooden shutters there)


Above: Caylee inspecting the gutters (Temporary Front Entrance Doors)


Above: Portico frame up

Thursday, November 25, 2010

More Action, but here comes the rain....

Went to the block again (a little obsessed) on the 23rd to have a look and found that the window/sliding doors frames have been delivered. More roof trusses have been added. Went again late on the 24th but the frames weren't installed yet (got my hopes up) although they had completed more work on the roof trusses & had the portico frame up. It is expected to be wet over the next week, so not expecting too much to happen.



Above: Alfresco coming along




Above: Walk in Pantry

Above: Laundry

Above: Dining/kitchen/Lounge rooms

Tuesday, November 23, 2010

Roof Trusses started!

Went Down late yesterday (22nd Nov) to find they have started the roof trusses (poor quality mobile phone pictures)



Sunday, November 21, 2010

More Frame

Went to the Block yesterday (20th Nov) and they have done more work on the frame, most rooms complete. Had a good walk through the rooms & very happy with the room sizes especially the walk in Pantry.
Above: Front Right




Above: Front Left (Garage)
Above/Below: Rear of House
Above: Front (Main Bedroom)

Thursday, November 18, 2010

Frame Started!

The frame has started - Photos were taken on the 17th November at Midday, Hopefully the rain holds off for the next few days & next week.

Tuesday, November 16, 2010

We have a scrape, a slab & Frame delivery

Yay! we finally have a start on our Block. On the 4th November we had a site scrape to get the levels right. On the 5/6th they boxed up ready to pour the slab. On the 9th they poured the slab! Checked again late on the 15th and they have marked out the slab ready to start putting the frames up. All the Wood was has been delivered to the slab also.




Above: Looking Down side of house towards rear of garage
Above: Alfresco & view of Backyard


Below: All Boxed up
Above: Footings for the Pillars & Verandah.



Above: Meter Box
Above: Garage Front Entry
Above/Below: It's a Scrape!