We finally got our Building contract on the 5th September and will read through in depth to understand the finer details of everything. We originally made quite a few changes to the original plan and they are:
-Extend the garage to approx 7m wide with rear roller door (for backyard access)
-Extend the 1st WIR in line with front of house
-Turned the 2nd WIR to face hallway to use as a storage cupboard.
-Made the Living room into a 5th bedroom (wall & doors)
-Extended the Games room back 1.2m to use as dedicated Home theater and added wall/doors
-Sliding door between kitchen and play room, and sliding door to study
-Doors to the en-suite
-Upgraded the carpet underlay (rubber)
-Extended the rear kitchen bench/cupboards/splash-back 40cm
-Added top cupboards to Laundry
-Put a 2nd manhole in the Garage
-Added a raised floor to rear of home theater with steps
-Added 15 additional power points
-Opted for a 700mm wall oven instead of the 600mm standard
-Opted for Ducted Refrigerated Cooling with 16 ceiling outlets instead of the standard Evaporative Cooling.
-Added 6 junction boxes outside & 3 external power points
We have gone with the Provincial facade that has a nice verandah also.
So it has gone from a 35.88sq size house to a 38.81sq house. Very Big with our Extensions to the plan.
Here is some Pictures of the Facade & Floor plan:
Our Changed Plan:
Original House Plan: